Starting Work on The River Went in Yorkshire

Although this is the start of what is planned to be a wider project that tackles multiple issues throughout the full length of this heavily-modified river, the first set of works are shaping up really pleasingly. 
Click Picture to Launch on YouTube
Alec and the rest of the YWT team have made impressive progress to organise and deliver the program of works that we designed on just around 1 km of the River Went, on a project supported by the Environment Agency.

It was particularly impressive due to a last minute loss of the previous project manager due to a career move. In the video you can see how Alec worked with the WTT to power through the first, steep part of the learning-curve on in-river structural improvements to a heavily-modified river.

The main challenges stemmed from the historic realignment of the channel (and general lack of in-stream structure/debris necessary to create vital habitat for different lifecycle stages of fish and other aquatic life). Coupled with the relatively low gradient and fine particulate material/potential associated diffuse-pollution inputs from upstream, this had made the channel very uniform (boring) and also lacking in diverse substrate (bed material).

While the future parts of this project will explore ways of improving land-use (and other measures) to reduce the particulate material runoff, the creation of alternating scour and deposition in this section should significantly increase the complexity (and hence value) of the habitat here. There is also, now a massive amount of extra cover from predation - which will help to keep populations of predators and prey in a more resilient balance.

The increased complexity (and scour/deposition processes) were complemented by the "seeding" of gravel upstream of some of the new "roughness-generating" structures in the channel. Spate flows redistributing that gravel should mimic the creation of spawning conditions that have been historically cut-off by changes to land-use (open-cast mining has inverted top and sub-soil horizons in the upper catchment!). 

Natural gravel inputs have also been constrained by the channel being straightened and locked in place. Normally, the gradual movement of a channel across a floodplain would cut into gravel "lenses" in the banks and continually replenish supplies to species that need gravel to breed.

You can see Alec describing this first phase of works in the embedded version of the video here:


Comments

Popular posts from this blog

First Survey Record of Wild Trout Returning to Lyme Brook Habitat Works Site!

You may have seen the first three phases of works on the middle reaches of the Lyme Brook (shown in previous blogs Here and Here) from project works that began in 2015...

Well although the first surveys after that work found some nice coarse fish populations - there was no cold hard evidence that any trout had found the newly-improved habitat...Until now!
I received a phone call today from Matt Lawrence who is the EA's Catchment Host for the Trent Valley Catchment Partnership (with key partners Groundwork West Midlands and the Wild Trout Trust who conceived and delivered the habitat works). Matt told me that he'd had some exciting preliminary reports from a EA Midlands fisheries surveys team. Their survey on 7th September had caught several wild trout as part of their sample on the habitat works site.
These are the first modern records of trout in the brook and is also the exciting news that we have been waiting for on these first phases of work to create spawning, juvenile an…

How Volunteers in Sheffield Make Big River Habitat Projects Successful

You've done a big, ambitious partnership project to deculvert a section of urban stream, but now the civil engineering contractors have gone to their next job. The site is left to mature...what next? Very seldom does this kind of project have any budget for ongoing ecological monitoring (which is a frequent and justified criticism of habitat improvement works - the lack of ecological effect data).

The same can be said for general "husbandry" of the site - whether it be litter or invasive plant control; or even fairly substantial running repairs...

Step in SPRITE (Sheffield Partnership for Rivers in Town Environments) whose site you can check out on http://www.sheffieldsprite.com, the Sheffield Trout in the Town group and a supporting donation of pre-established planted coir products from Salix River and Wetland Ltd. (with their site here: https://www.salixrw.com)

You can see SPRITE talking about their aquatic invertebrate monitoring and see their repair and site care wo…

Porter Brook Deculverting on Brazilian TV

The deculverting and stream habitat improvement project was picked up by the European news team for Brazilian (!) channel Sistema Brasileiro Televisão or "SBT". Their piece looked at what had been done in Sheffield by the partnership project between Sheffield City Council, EA and Wild Trout Trust to see what could be applied in Brazilian cities and their watercourses.

The Tagline was "What can Sao Paolo Learn from Sheffield? How Industrial Sheffield Uncovered its Rivers" and went out to their reported audience of around 20-million viewers.

If you fancy brushing up on your Portuguese, you can check out the report here:


The embedded news item can be viewed on the SBT site by Clicking Here.